Timeline & Schedule

line
Image
image

May 2007
Cashflow Schedule
(xls, 540k)

image

December 2006
Full Construction Timeline
(jpg, 700 KB)

 

 

image

Project Milestones

Activity Early Start Early Finish %
Groundbreaking Apr. 2005   100%
Excavation and Piles,
Sheeting & Shoring
May 2005 Nov. 2006 100%
Secant Pile Installation Complete   Jul. 2006 100%
Foundations Feb. 2006 Nov. 2006 100%
Start Structural Steel Seq. 1

May 2006

  100%
Start Structural Steel Seq. 2 Ju. 2006   100%
Structural Steel Topout   Sep. 2006 100%
Completion of Concrete on Metal Deck   Nov. 2006 100%
Turn on Permanent Heat Dec. 2006 Jan. 2007 100%
Completion of Building Dry-in April 2007   0
Air Balance Complete Aug. 2007   0
Turn Permanent Cooling On Aug. 2007   0
Complete Fire Alarm & System Testing   Sep. 2007 0
Completion of Building Finishes   Nov. 2007 0
State Fire Marshall Final Inspection   Nov. 2007 0
Substantial Completion   Dec. 2007 0
Obtain TCUO Dec. 2007   0

Final Completion

  Dec. 2007 0